|
|
![]() "It
is impossible for ideas to compete in the marketplace if no forum for Chapter Four: Office Planning & Design
Construction
Management
Creating
an office facility, or renovating or reorganizing existing office space,
requires
a logical and organized approach. Once the planning and design stages
have
been completed, then purchasing of materials and construction can begin.
Construction management, which oversees the complicated business of turning
working drawings and design sketches into physical reality, must be competent
and
thorough. Timetables and schedules, along with attention to detail and the
ability to coordinate many trades and professions, are probably the most
important tools of construction management. The actual procedures that should be
followed are examined in detail in this chapter. How these procedures fit into
the overall project can be further clarified by studying the "Space
Planning and Design Procedures Outline" in the Appendix (parts IV and V, in
particular).
Construction
Survey
Construction
and purchasing management go hand in hand. The first step must be to
check every drawing, schedule, and piece of paperwork relevant to the project.
Once the working drawings and schedules are completed and accepted,
the
next priority is to compile a final site survey to check that the drawings and
specifications are correct and applicable to the building involved. Obvious
points that need to be checked are the following:
1.
Check that all measurements and dimensions are accurate on the documents
relative to the building.
2.
Check that power sources and outlets correspond to equipment and that
positions are correct, thereby ensuring that relative voltage requirements for
special equipment are properly supplied.
3.
Where scale drawings are used, check them by calculating the actual site
measurements from the scale drawings and then comparing these figures
with
actual on-site measurements.
4.
Check all the following plans (sometimes several, or all, will be combined on
one plan) according to instructions in items 1,2, and 3 (if
applicable):
(a)
Final layout (showing layout of furniture, planters, and so on).
5.
Check that all purchase orders agree in numbers and specifications with
the
working drawings, layout plans, and other design documents.
This
last item is important since mistakes at this beginning stage can lead to over
ordering or shortages at a later stage. Details such as colors and catalog
numbers need to be carefully checked and initialed to prove they agree with
data on the drawings and purchase orders.
Building
Permission:
The
law demands that certain agreements be obtained for building work, and plans
and documents must be submitted to and approved by the relevant bodies before
orders are placed or construction begins. Professional assistance at this stage
is a wise investment. Almost without exception, plans need to be approved by
and permits obtained from:
1.
the building department;
2.
the safety and health administration;
3.
the relevant zoning authority.
Managing
Construction Work:
Once
all drawings and related construction documents have been approved, the
firm
can proceed with the project, adopting one of the three following approaches:
1.
Establish a procedure, or employ the organization's existing supply
procedures, to manage the project within the organization.
2.
Employ a general contractor to manage the project.
3.
Employ a construction management company to coordinate the operation.
(Some of the major offices planning organizations have a construction
management
division. This can be a very satisfactory arrangement because
one
firm is therefore responsible for the whole project, and much confusion can
thereby be avoided. Furthermore, since their work on this stage
reflects on the quality of the total design service they offer to clients, they
are apt to be conscientious and thorough throughout the project.
Obtaining
Bids:
Whether
a construction management company or the organization itself obtains bids,
several important considerations should be observed in the process:
1.
Be certain to obtain references on both the quality of past work and the
financial stability of any contractors or trades people who are asked
to
bid.
2.
Ensure that all bidding contractors include, within their prices, the provision
of adequate insurance coverage, such as:
(a)
workers' compensation insurance;
3.
Ensure that all manufacturers' warranties or guarantees, as to methods of
installation,
workmanship, and materials, are contained in construction
contracts
and subcontracts.
4.
Always obtain a quantifiable number of bids (normally three or more)
and
cross-check them for additions, omissions, and clauses of liability.
5.
Where possible, include time limits and completion dates within both bids and
contracts, with compensation clauses for late completion. This will enable
more control in planning schedules.
Expediting
Orders:
Obtaining
materials and services is a management technique that requires discipline on the
part of both the buyer and the
supplier. The following procedures will help both parties avoid trouble. The
party placing the order should:
1.
Always make sure to allow as much time as possible between placing the
order
and the delivery data. Ordering anything at the last minute is just asking for
trouble.
2.
Give as much information and detail as possible. Include all catalog numbers
and codes and a full description of what is being ordered.
3.
Obtain the expected delivery date as soon as possible and have the manufacturer
or suppliers confirm this detail in writing.
4.
Check every potential delivery problem in advance and make arrangements
to overcome them (for example, book elevator time in advance, check dimensions
to make sure that the goods can actually be gotten into the building, hire
cranes and any required machinery well in advance,
and
plan delivery routes for bulky items). Always ask the manufacturer or supplier
for advice regarding potential delivery problems. Where possible,
have the supplier send a technical representative to check out site conditions
well in advance and, where applicable, to advise on storage
requirements and so on. Most manufacturers will supply a technical
representative to be present during installation of expensive items (such as
carpets, equipment, and so on). Inquire about this service when placing the
order and include it in the purchase order or contract.
5.
Make quality checks prior to
delivery. It is wise to visit the factory or warehouse prior to taking
delivery to check specifications and quality of
goods
before they are shipped, especially when the items are custom made
or
a large expenditure is involved.
6.
Maintain a system of regular checks on developments after placing the order.
Do not just order and forget it.
Constant and regular checking
should
be made to ensure that delays do not occur and that deliveries take place on
the day and time agreed.
7.
Include a "change order" clause in the contract. If, during
construction,
changes
in layout or materials occur, they can cause serious problems.
Therefore,
no changes should ever be made without documentation and
relevant
rescheduling. A clause in all contracts and purchase orders should
be
inserted to cover this. The following is an example of such a clause: "Any
changes in specifications, delivery, or numbers involved must be covered by an
official 'change order." Any changes in layout, drawings,
or
materials that cause changes in construction costs must be handled by
a
change order." No change of work will be accomplished without
written approval."
Construction
Schedules:
Obviously,
construction must be scheduled so that the work of one trade is not damaged
by the work of others. For this reason, the construction manager should ascertain,
while obtaining the bids, the requirements of the contractors and suppliers,
including (but not limited to) the following information:
1.
Will the work be "wet" (messy and dirty - for example, plastering)
or "dry" (clean and tidy - for
example, fitting carpets)?
2.
What site provisions will be needed (for example, electricity, storage, access
to water, and so on)?
3.
What special delivery provisions are required (such as cranes, special
machinery,
specific access points)?
4.
What is the time frame involved? (If two trades - such as painting and
fitting
the carpets - overlap, the results could be disastrous.)
Before
construction commences, a spreadsheet or contract procedure form will
have to be prepared, upon which the activities of the trades people and the
deliveries of materials and furniture can be planned (see Exhibit 4-1).
Basically, trades follow a traditional schedule; however, each project
differs in one aspect or another. A good basic
guide for scheduling work and deliveries of associated materials
is the following:
1.
Demolition of old unwanted structures (such as walls) and making building
alterations (such as replacing windows or making openings
for
new doorways or blocking up unwanted ones).
2.
Structural and building work (such as building new walls, installing plumbing,
or creating openings in floors for stairways).
3.
Ducting and electrical work (such as rewiring and installing new ducting for
air conditioning).
4.
Building finishes (for example, plastering, installing partitions or heavy
wall
finishes, such as tile, etc.).
5.
Wet trade flooring (for example, laying new floors or screeds, marble tile
floors, etc.
6.
Painting.
7.
Dry flooring (for example, wood floors that require sanding).
8.
Custom cabinet work (such as custom desks and so on).
9.
Door hanging (including hardware).
10.
Glasswork (interior glass walls, screens, and so on).
11.
Wall coverings (such as wallpaper, cork, hessian, and so on).
12.
Laying carpet.
13.
Furniture layout.
14.
Planter layout.
15.
Artwork and signs.
16.
Finishing, remedial work, and cleaning.
Final
Survey:
When
construction and the installation of furniture and equipment are complete,
the total space needs to be checked once more against all the original plans,
drawings, schedules, and documentation (including change orders) to ensure
that nothing has been overlooked or forgotten. Items that are outstanding or
have been delayed should then be listed on a checklist
for follow-up.
Move-In:
Once
the follow-up work is done, the facility is complete. At this time, if everything
has gone well, the facility is at its best. It's as new and as perfect as the
client,
the
executive planner, the office planner, the designers, and the contractors have
been
able to make it. Once the photographs have been taken and the executives
of
the company have had their tour of inspection, the space is ready for habitation
- that is, it is ready to receive the people who will make it work.
The
following steps to ensure a successful move-in need careful attention
but
are well worth the effort:
1.
A pre-move meeting, or series of meetings, should be arranged with department
heads and key personnel to organize the transfer of files, records, and other
effects from the old space to the new one. Careful labeling and loading of
these materials are, of course, essential; and, for a large-scale move, it is
wise to color code labels
or boxes to identify departments.
2.
Staff meetings should be arranged to explain the move and its consequences.
If possible, pre-move tours of the new facility should be arranged
for
every employee (in department or status groups).
3.
A brochure describing the new facilities (with maps) should be produced
for staff use.
4.
Department heads should tour their areas several days before the move-in to
give last minute advice and final briefings to those overseeing the move
and
to their staffs.
5.
Details of transport, parking, and such information should be circulated to
all staff.
6.
A system should be organized to receive and deal with complaints and
suggestions
during the immediate post move period.
The
move should never be hurried, but it should be a disciplined operation. It
heralds the beginning of a new era for the organization, so its success is important
for reinforcing a positive outlook among all members of the firm. As a
final
note, on the first day in the new facility, holding a celebration, however
small,
can be very rewarding to all concerned.
Furthermore,
photographs of the event will be useful to the public relations and for use by
the personnel department.
Instructional Programming: Chapter Four
1.
___________and _________are the most
important tools of construction management
(in addition
to the working drawings and specifications received
from the planners and designers).
2.
The person in charge of construction management can assume that all working
drawings are correct when received from the planners and designers.
(
) True
3.
Colors and catalog numbers need to be ___________
and
then ____________ to prove they agree with the
numbers indicated on drawings
and purchase orders.
4.
Plans normally need to be approved by, and permits for building
obtained from, the ____________ department, the
safety
and ____________ administration, and the relevant
____________ authority.
5.
What are three approaches a firm can adopt to organize
the
management of construction work?
6.
When obtaining bids for work, the construction manager
should
obtain references on the ____________ of
past
work and ____________ stability of all contractors
and
trades people.
7.
Construction trades can be divided into what two descriptive types?
8.
The purpose of a spread sheet or a contract procedure form is to:
(a)
plan trade activities and deliveries of materials and furniture.
9.
Wet trade flooring (for
example, laying new floors or screeds) should always be completed before
electrical work begins.
(
) True
10.
When construction and the installation of furniture and equipment
are complete, a ____________ survey should be conducted to check the total
completed space once more
against
the original plans, drawings, schedules, and documentation.
11.
For a large-scale move, it is wise to ____________
labels and boxes to help
identify the
departments
to which they should be delivered.
12.
Prior to the move-in, a ________ describing the new
facilities
should be produced for staff use
13.
Every employee should be given a chance to tour the new facility
prior to move-in.
(
) True
Chapter
One: Office
Planning & Design
Chapter
Two: Office
Planning & Design
Chapter
Three: Office
Planning & Design
Chapter
Five: Office
Planning & Design Disclaimer
The Business Forum, its Officers, partners, and all other Home
Calendar The Business Forum Journal
Features
Concept History The Business Forum webmaster: bruceclay.com
|